Phased Warehouse Exterior Repaint
Case study · Light Industrial · Richmond
This Richmond warehouse was being converted for a new public-sector tenant when the property manager brought us in to repaint the exterior. A general contractor was running the site, with plumbers, electricians, HVAC technicians and concrete crews working at the same time.
We repainted more than 35,000 sq. ft. of concrete tilt-up wall across three elevations of the 113,000 sq. ft. building. The red canopies, entrance steel and man doors were changed to the tenant’s blue, and the red accent band on the walls was repainted to match so the building reads as one scheme. The glass-topped steel canopy and the full run of railing were refinished to match.
Before any paint went on, the panel joints were recaulked and concrete repairs were completed. We ground off old steel bolts left sticking out of the walls, primed them with a rust-inhibitive primer and caulked over them, then recaulked the remaining blemishes. The walls were finished in an exterior acrylic. The steelwork, railings and doors were coated with an industrial single-component urethane for colour retention and wear.
Each morning our crew signed in, held a joint safety meeting with the general contractor’s superintendent, and cautioned off its own work zone before starting. Other trades stayed out of our zone and we stayed out of theirs. We moved elevation by elevation as scaffolding came down and bins were shifted.
The property manager has since brought us back for work on several of their other buildings.
Safety on jobs like this: Only trained operators run our lifts, a harness is worn on boom lifts, and each lift is inspected before use. Lifts, Fall protection
More in Richmond: Warehouse painting in Richmond
Planning similar work?
Price my project →Case study: how a job like this runs
We run every site the same way. On a phased exterior repaint, the steps look like this.
-
Exterior walkthrough
We walk every elevation and note failing paint, rust bleed, cracks and failed sealant, and what is stored against the walls.
-
Scope and planning
The quote sets out the scope by surface: walls, man doors, railings, canopies and entrance steel. Sealant is measured and priced by the linear foot.
-
Phasing and communication
The work is phased by elevation, around the general contractor’s schedule and the other trades on site. Everyone knows which wall is next and when it needs to be clear.
-
Safety and traffic control
Lift work follows WorkSafeBC requirements. The crew signs in daily, joins a safety meeting with the general contractor, and cautions off its own work zone before starting. Anything not being painted is protected.
-
Washing and surface preparation
Every surface to be coated is pressure washed. Failing paint is scraped and sanded, old steel bolts are ground flush, and failed sealant is removed and replaced.
-
Inspection before coating
Washed surfaces are left to dry fully. The foreman checks the prep and the new sealant before any coating goes on.
-
Priming
Ground-off bolts and rust areas get a rust-inhibitive primer and are caulked over. Doors, railings and canopies get a bonding primer.
-
Finish coats
Concrete walls get an exterior acrylic, with the accent band cut in to match the steel. Steelwork, railings and doors get an industrial single-component urethane.
-
Cleanup
Masking and protection come off, old sealant and paint debris are removed, and the lifts leave the property.
-
Walkthrough and handover
We walk the building with you at the end of each phase, then again when the whole job is done.
Standards: Work follows MPDA guidelines and MPI standards, SSPC standards for preparing steel and concrete, and each manufacturer's data sheet for prep, application and drying times.
More light industrial projects
Before & after
Before & after Automotive Shop Floor
This floor had years of embedded oil contamination that regular washing and etching could not fully remove or prepare for a new coating system. To ensure proper adhesion, we had the surface shot blasted to remove contamination and open up the concrete profile. The resulting clean, even surface provided an ideal mechanical bond for the epoxy system, ensuring long-term durability and performance.
100,000 sq. ft. Warehouse Interior
This 100,000 sq. ft. warehouse underwent a complete interior transformation, turning a dark, dirty, and difficult-to-lease space into a bright, modern facility. Our team first used a phosphoric acid treatment to properly etch the galvanized steel ceiling, ensuring maximum coating adhesion and long-term durability. We then applied a clean white finish to the ceiling, walls, and structural columns while highlighting the lower steel with safety yellow for improved visibility and workplace safety.
Looking for a free quote?
Tell us about your building and the work you need. We’ll get back to you to set up a site visit.
Phones answered 7am–7pm, every day. Quote requests are acknowledged the same day.
- Bonded & insured
- Member in good standing of DC38
- Red Seal painters on our crews
- Lead jobs done by lead-trained crews